Repair/Removal of Railroad Crossings

2 Aug, 2017

Listed below are the Rail Road crossings to be removed or repaired over the next 15-20 months pending railroad company cooperation, weather and funding.

Note: This list is in no particular priority order.

2nd Ave NE Crossing – This track will remain for use, will make repairs.
1st Ave NE Crossing – This track will remain for use, will make repairs.
East Central Ave Crossing – State Route – can be removed or repaired, pending GDOT.
2nd Ave SE Crossing – to be removed.
5th Ave SE Crossing – to be removed.
6th Ave SE Crossing – to be removed.
9th Ave SE Crossing – to be removed.
Hillcrest Crossing – to be removed.
12th Ave SE Crossing – to be removed.
15th Ave SE Crossing – to be removed.
26th Ave SE Crossing – to be removed.